2025 Beach Renourishment Project Timeline

Pending final approvals, the preliminary schedule has been updated. The following timeline may be subject to change depending on external factors beyond the Town's control.

  • Phase 1 - Port Royal (the Heel), Fish Haul and Pine Island.
    • Contractor mobilizes in July 2025.
    • Work begins in August 2025 at Pine Island.
    • Work completed November 2025 at The Heel/Port Royal.
  • Phase 2 - Central Island, South Island and South Beach.
    • Work begins in November 2025 at the north end of Central Island beach.
    • Work completed May 2026 at the south end of South Beach.
  • Phase 3 - Pine Island Breakwater Structures.
    • To be determined - anticipated in 2026.

* Timeframes are subject to change

Project Fill Placement Areas